November 5, 2026
The Cortez Bridge replacement is getting started in the same weeks that the fishing village starts its busiest stretch of the year. FDOT's senior projects engineer Dustin Spears gave a tentative start date of November 9, and the first visible work is planned on the water north of the existing bridge, according to the AMI Sun. Stone crab season opened October 15. Christmas in Cortez is set for December 12, and the Cortez Commercial Fishing Festival returns February 13 and 14.
Most of how this winter will feel in Cortez comes down to one decision Manatee County made on October 20 about where the contractor parks its equipment. The work is being staged from the north side so that Cortez Road and the restaurant lots along it face fewer daily disruptions during the season.
The county bought the former Seafood Shack property in 2024 for $13 million. On October 20, commissioners voted 5-1 to license it to SEMA Construction as a staging area for four years, the AMI Sun reported. The site is divided into two areas. Parcel 1, at the south end, will hold semi-permanent structures, including a crane access trestle. Parcel 2 sits along the water north of the humpback bridge on 127th Street West. It will hold worker parking, material storage, and the assembly of forms and rebar cages that get loaded straight onto barges. The parcel will be fenced, gated and posted.
The volume of material explains why the location matters. SEMA representative Justin Oakes told commissioners the project should take more than 3,000 truckloads over the 1,200-day contract, or three to five a day on average. He said that without Parcel 2, the contractor would have relied heavily on the state right-of-way in front of Tide Tables restaurant, and that would have meant daily lane closures on Cortez Road.
According to the AMI Sun's coverage of the meeting, Tide Tables co-owners Karen Bell and Bobby Woodson said staging on that right-of-way would take away the restaurant's parking and nearly put them out of business. Woodson said the restaurant employs about 50 people and serves 500 to 1,000 customers a day. The approved agreement keeps staging out of the Tide Tables lot, and both owners endorsed it. FDOT's Spears made a similar point from the construction side. With the extra parcel, crews can work directly from the north side of the bridge and don't have to stage on the south side and move equipment under it.
The staging plan changed after the earlier community meetings. When the plan went to the county commission in June, Parcel 2 was meant for overflow parking for workers. Residents of the neighborhoods north of the bridge told commissioners they had agreed to light-vehicle parking there at a July meeting. They said they learned only days before the October vote that the site map had been relabeled to include material assembly. One speaker said more than 300 residents pass the Parcel 2 area to reach Cortez Road, by what he described as the only way in and out. Commissioner Jason Bearden cast the one vote against and said his concern was transparency.
The county also got something in return, because some of the delay was its own. Manatee County Utilities chief engineer Chad Butzow said the county's project to replace the water main under the Intracoastal Waterway is well behind schedule. The old main conflicts with the pilings SEMA needs to drive for the first stage of the bridge, work that was supposed to begin in June. In exchange for the land, SEMA agreed not to seek delay costs from the county or the state, which Butzow estimated at about $1.4 million. SEMA also has to build a docking, storage and fueling area for the county's Gulf Islands Ferry on the property and remove an existing house there.
Commissioner George Kruse said he did not want the bridge delayed again and summed up the vote this way: "The best way negotiation works is everyone walks away a little bit unhappy."
The construction is only part of what's shaping the season. The weather is doing the rest. Jim Gowett, manager of Star Fish Company Market and Restaurant, told the AMI Sun that the local stone crab catch started slow because the water has been unusually clear.
"They're barely catching anything because the water is so clear right now. The crabs aren't moving." — Jim Gowett, Star Fish Company, to the AMI Sun
He explained that in clear water, stone crabs stay buried in the mud where predators can't spot them, so they don't walk into traps. Most local traps are within five miles of shore, and with fuel prices high, some boats are losing money on each run. In the meantime, Star Fish has been buying claws from the Florida Panhandle, where crabbers are landing mostly jumbo and colossal sizes. Colossal claws at Star Fish sell for about $45 a pound, which works out to one or two claws.
Adam Sears, general manager of the Swordfish Grill and the Cortez Kitchen, told the paper that fuel is "as high as it gets" while the price paid to crabbers has barely moved. He also pointed to competition from large fleets elsewhere that can land 1,000 or 2,000 pounds at a time. The season runs through May 1, which leaves Cortez boats plenty of time to recover if the water clouds up. For now, a claw dinner on the village waterfront this month may well come from boats far up the coast.
FDOT's schedule, as the AMI Sun laid it out from the October 20 public information session at Kirkwood Church, puts several phases into the same months as the village's best-known events. FDOT calls every date on it tentative, and its own project page expects the first traffic shift somewhat sooner, by the end of this year.
| When | In the village | On the bridge, per the current schedule |
|---|---|---|
| Nov. 14, 2–4 p.m. | Music on the Porch on the Burton Store porch, plus the Vintage Buoy Workshop at the Folk School | Fall work: south sidewalk closed, pilings driven north of the existing bridge, temporary trestle and Hunters Point Way under construction |
| Nov. 17 | Mastering Sourdough at the Folk School | Same fall stage |
| Nov. 28 | Music on the Porch canceled for the holiday | Same fall stage |
| Dec. 12, noon–3 p.m. | Christmas in Cortez, free, with Music on the Porch on the Schoolhouse porch at 2 p.m. | Same fall stage |
| Jan. 27 to Feb. 26 | Folk School classes resume with Pasta Making on Jan. 27 | Early 2027: traffic moves to a temporary diversion roadway and Hunters Point Way opens |
| Feb. 13–14, 10 a.m. | 45th Cortez Commercial Fishing Festival | Diversion roadway in use |
| Spring 2027 | Stone crab season continues to May 1 | 127th Street West closes temporarily, with traffic detoured via Hunters Point Way |
Christmas in Cortez has a change of its own this year. The day includes Santa, the AMI Privateers handing out gifts, bounce houses, crafts, student performances and food trucks. The Florida Maritime Museum's Christmas in Cortez page says admission, parking and activities are free and that the museum building will be closed during the event for structural rehabilitation. Music on the Porch, which the museum co-hosts with the Cortez Cultural Center on the second and fourth Saturdays, takes December 26 off as well. The festival's organizers at F.I.S.H. chose "Cortez Fishes For You – Since the 1800's" as the 2027 theme, and food vendors have until November 30 to apply.
Spring is when the overlap gets tighter. Woodson warned commissioners that extra lane closures could back traffic up to 75th Street during the busy spring season. Running the truck traffic out of Parcel 2 is the county's answer to that concern. The 127th Street West detour scheduled for spring 2027 will still overlap the end of stone crab season.
Cortez Road will not close completely at any point. Spears said there will be intermittent lane closures and that "those can happen any time during the day." Some changes affect walkers and riders specifically:
After this winter, the schedule moves in large steps. FDOT's project page describes Phase 1 as building the north half of the new bridge next to the existing one. Traffic then shifts onto it so the old bridge can be demolished in Phase 2. The AMI Sun's schedule puts the start of Phase 2 in spring 2028, while FDOT's page says mid-2028. The full bridge is expected to open to traffic in summer 2029, with punch-list work wrapping up in late 2029. FDOT posts updates on its Cortez Bridge project page, and its schedule there is the one to check before a festival weekend.
If you're thinking about how four years of construction might affect a west Bradenton home near Cortez Road, Jessica Sold My Home can go over the timeline with you and how it fits your plans. Schedule a Free Market Consultation, and we'll start with the phase dates that apply to your street.
Stay up to date on the latest real estate trends.
Searching for your dream home in the Sunshine State? Look no further! Jessica Ross is your dedicated Florida real estate expert, ready to guide you on an exciting journey towards finding the perfect property.